Industria Paraguaya de Alcoholes S.A. (INPASA)

Located in San Pedro, Paraguay, the second INPASA plant was commissioned in March 2018. The plant produces 700,000 liters per day of motor fuel grade ethanol, using corn as a feedstock. In addition, it produces a high-quality DDGS product. Start-up was completed ahead of schedule and full production capacity was achieved within 2 months of commissioning.

KATZEN provided to INPASA our detailed process design package and continues to provide off-site and on-site support for construction, commissioning, start-up, and plant operations.